GRID FREQUENCY
49.95 hz

CURRENT DEVIATION RATE
3.03 Rs./KWh

STATE DEMAND MET
6357.00 MW

STATE GENERATION
5413.77 MW

NET TIE FLOW
-1430.34 MW

Last updated on 22-02-2019
at 08:17 pm
Revision of Schedule currently in force


Revision 9
Deviation Bill
Select Year:
Description Date Of Issue Remarks
Deviation Bill for the period
28-01-2019 to 03-02-2019
19-02-2019
Deviation Bill for the period
21-01-2019 to 27-01-2019
16-02-2019
Deviation Bill for the period
14-01-2019 to 20-01-2019
06-02-2019
Deviation Bill for the period
07-01-2019 to 13-01-2019
02-02-2019
Deviation Bill for the period
31-12-2018 to 06-01-2019
08-02-2019 REV-01
Deviation Bill for the period
31-12-2018 to 06-01-2019
28-01-2019
Deviation Bill for the period
31-12-2018 to 06-01-2019
25-01-2019
Deviation Bill for the period
24-12-2018 to 30-12-2018
15-01-2019
Deviation Bill for the period
17-12-2018 to 23-12-2018
11-01-2019
Deviation Bill for the period
22-10-2018 to 28-10-2018
31-12-2018 REV-01
Deviation Bill for the period
10-12-2018 to 16-12-2018
04-01-2019
Deviation Bill for the period
03-12-2018 to 09-12-2018
27-12-2018
Deviation Bill for the period
26-11-2018 to 02-12-2018
19-12-2018
Deviation Bill for the period
19-11-2018 to 25-11-2018
13-12-2018
Deviation Bill for the period
30-07-2018 to 05-08-2018
11-12-2018 Rev-02
Deviation Bill for the period
29-10-2018 to 04-11-2018
11-12-2018 Rev-01
Deviation Bill for the period
12-11-2018 to 18-11-2018
07-12-2018
Deviation Bill for the period
05-11-2018 to 11-11-2018
28-11-2018
Deviation Bill for the period
29-10-2018 to 04-11-2018
22-11-2018
Deviation Bill for the period
22-10-2018 to 28-10-2018
16-11-2018
Deviation Bill for the period
15-10-2018 to 21-10-2018
05-11-2018
Deviation Bill for the period
08-10-2018 to 14-10-2018
02-11-2018
Deviation Bill for the period
01-10-2018 to 07-10-2018
01-11-2018
Deviation Bill for the period
24-09-2018 to 30-09-2018
30-10-2018
Deviation Bill for the period
17-09-2018 to 23-09-2018
27-10-2018
Deviation Bill for the period
10-09-2018 to 16-09-2018
12-10-2018
Deviation Bill for the period
03-09-2018 to 09-09-2018
12-10-2018 REV-01
Deviation Bill for the period
06-08-2018 to 12-08-2018
03-10-2018 Revision 01
Deviation Bill for the period
03-09-2018 to 09-09-2018
29-09-2018
Deviation Bill for the period
27-08-2018 to 02-09-2018
20-09-2018
Deviation Bill for the period
20-08-2018 to 26-08-2018
14-09-2018
Deviation Bill for the period
30-07-2018 to 05-08-2018
14-09-2018 REV-01
Deviation Bill for the period
13-08-2018 to 19-08-2018
08-09-2018
Deviation Bill for the period
06-08-2018 to 12-08-2018
06-09-2018
Deviation Bill for the period
30-07-2018 to 05-08-2018
28-08-2018
Deviation Bill for the period
23-07-2018 to 29-07-2018
21-08-2018
Deviation Bill for the period
16-07-2018 to 22-07-2018
11-08-2018 REV-01
Deviation Bill for the period
09-07-2018 to 15-07-2018
07-08-2018
Deviation Bill for the period
02-07-2018 to 08-07-2018
30-07-2018
Deviation Bill for the period
25-06-2018 to 01-07-2018
20-07-2018
Deviation Bill for the period
18-06-2018 to 24-06-2018
14-07-2018 REV-01
Deviation Bill for the period
11-06-2018 to 17-06-2018
14-07-2018 REV-01
Deviation Bill for the period
18-06-2018 to 24-06-2018
12-07-2018
Deviation Bill for the period
04-06-2018 to 10-06-2018
28-06-2018
Deviation Bill for the period
14-05-2018 to 20-05-2018
14-06-2018 REV 01
Deviation Bill for the period
11-06-2018 to 17-06-2018
05-07-2018
Deviation Bill for the period
28-05-2018 to 03-06-2018
23-06-2018
Deviation Bill for the period
04-06-2018 to 10-06-2018
14-06-2018 Rev-01
Deviation Bill for the period
14-05-2018 to 20-05-2018
05-06-2018
Deviation Bill for the period
21-05-2018 to 27-05-2018
12-06-2018
Deviation Bill for the period
07-05-2018 to 13-05-2018
02-06-2018
Deviation Bill for the period
30-04-2018 to 06-05-2018
31-05-2018
Deviation Bill for the period
23-04-2018 to 29-04-2018
28-05-2018
Deviation Bill for the period
16-04-2018 to 22-04-2018
15-05-2018
Deviation Bill for the period
09-04-2018 to 15-04-2018
08-05-2018
Deviation Bill for the period
02-04-2018 to 08-04-2018
05-05-2018
Use green power and make the future pollution free       ||       Do not neglect safety in site       ||       Save electricity
Website optimised for 1024 x 768 screen resolution